A mandatory framework
Every off-plan sale of a home or professional premises must comply with articles 618-1 to 618-20 of the Code of Obligations and Contracts, or it is void, whoever the seller is. The regime comes from Law 44-00, amended by Law 107-12 (dahir of 3 February 2016).
Reservation contract, then preliminary contract
The reservation contract is optional. It can only be signed once the building permit has been granted, is valid for six months at most and cannot be renewed. You have one month to withdraw, and your money is then refunded in full within seven days. Meanwhile it sits in a special bank account that the seller can neither use nor have seized.
The preliminary sale contract is signed after the building permit, by authentic deed or by an authorised professional, and initialled on every page. It must state the land title number, the building permit date and number, the price and payment terms, the delivery date and the references of the guarantee.
The seller also draws up specifications matching the approved plans, signed by both parties. For titled land, they are filed at the land registry together with the architect’s plans. Reservation and preliminary contracts are exempt from registration duties.
Read the full guide
Enter your details to read the rest of this guide, and of the five others. A consultant can also answer your questions on WhatsApp.
Payments that follow the works
Article 618-6 sets the maximum share of the price you can pay at each stage:
- 5% when the reservation contract is signed;
- 5% when the preliminary contract is signed, or 10% if there was no reservation;
- 10% when works start;
- 60% over three phases, split as the parties agree: foundations up to ground-floor level, structural work of the whole building, then finishing work and occupancy permit;
- 20% when the final contract is signed and the keys are handed over.
The guarantees
After the preliminary contract, the seller must provide either a completion guarantee or a guarantee that your payments will be refunded. Whoever drew up the contract may not release money to the seller until this guarantee covers everything you have paid.
Once your payments exceed half the price, you can have a protective entry (prénotation) registered on the land title: it secures your rights and carries over to your plot when the title is split.
Any payment demanded before the reservation or preliminary contract is signed is void.
Delays and penalties
The seller may extend the delivery date once, by six months at most, provided you are told at least one month before the deadline. Late payment by the buyer, like late works by the seller, carries an indemnity of 1% a month, capped at 10% a year, starting one month after formal notice.
If delivery does not happen on the agreed date, extension included, you can terminate the contract with no penalty and receive, on top of your refund, 20% of the sums paid. You can also assign your contract to someone else, in the same form.
Handover
The home counts as completed once the occupancy permit or certificate of conformity is issued. Within 60 days, the seller informs you and applies to split the land title; you are told within 30 days of the individual titles being created.
The final sale contract is then signed, and you become the owner when it is entered on your villa’s land title.
At CITYSTAR
At CITYSTAR, the reservation is signed before a notary and every payment goes through the notary’s office. The build is fully funded by the developer’s own capital: it depends neither on developer loans nor on off-plan sales. Your consultant gives you the detailed payment schedule for your villa, stage by stage.
This guide gives general information, up to date at the date shown. It does not replace advice from a notary, a lawyer or a tax adviser, who will take your own situation into account.